When to plan furniture during renovation in Batumi: measurement and installation preparation

Batumi Kitchen ·

Discuss furniture before the electrician positions sockets and the builders close the walls. A plan of cabinets, the kitchen and appliances is already needed at this stage. Manufacturing dimensions come later, with the finished surfaces taken into account. Split preparation into two stages: agree the layout and connections first, then prepare the apartment for final measurement and installation.

1. Give the builders a furniture plan

Mark the kitchen, wardrobes, bed, cabinets and appliances on one plan. Sockets must remain accessible behind or beside furniture, and switches must stay usable when doors are fitted. Give the same plan to the cabinet maker, electrician and plumber. Update it for everyone whenever the furniture layout changes.

A useful habit: keep the current plan in one folder with the date in its filename. Move old versions elsewhere. This keeps the electrician and cabinet maker working from the same drawing.

2. Agree finishes before final measurement

Built-in furniture depends on finished room dimensions. Plaster, tiles and flooring change alcove width and floor-to-ceiling height. Explain what still needs adding to the walls and floor. Recheck dimensions after changes that affect the furniture.

Record the flooring type and agree the installation order with both the flooring installer and cabinet maker. This is particularly relevant to floating floors and heavy fitted furniture. A blanket instruction to finish every floor before fitting cabinets cannot replace the flooring manufacturer's requirements.

Fitted bedroom wardrobe to the ceiling with a switch and socket beside it
Our bedroom wardrobe in Batumi. This type of furniture needs the finished room height, junctions and nearby socket positions agreed in advance.

3. Bring a skirting sample to the measurement

Show the skirting profile or its dimensions even if it has not been fitted. Mark door trims, window sills and wall projections. Agree where the skirting continues, where it ends and how the cabinet meets the wall. Resolve these details before manufacturing the carcass.

4. Photograph pipes and wiring before walls are closed

Save a full view of each wall and close-ups of utility routes. Record distances from clear reference points such as a corner, floor or doorway on a drawing. Give these records to the installer. Photos help identify routes; the installer checks the fixing location separately before attaching furniture.

For a wall-hung vanity or upper cupboards, identify the wall material and planned reinforcement locations. Agree preparation of the supporting wall with the builders before finishing it.

Wall-hung bathroom vanity during installation, before the basin is fitted
A vanity during installation from our mirror project collection. Agree wall preparation and connection positions before fitting wall-hung furniture.

5. Finish work that leaves moisture and dust

Before furniture delivery, agree the completion of plastering, screed, painting and other wet work in the installation area. Confirm drying times with the contractor and material instructions. Fix leaks and damp wall areas before installing furniture. Prepare a dry indoor space for storing components.

6. Check the full route from vehicle to room

Measure doorways, the lift cabin and entrance, and tight stair turns. Give the dimensions to the cabinet maker: a long wardrobe side panel must pass along the entire route. Ask building management about delivery access, lift use and permitted hours for noisy work. Clear the route before the installer arrives.

7. Leave space for assembly

Move belongings away from the wall and clear a working area for components. Agree floor and route protection, access to power and packaging removal. Arrange for someone to open the apartment and answer questions about the approved design on installation day.

A short installation checklist
PrepareGive the installer
Current designOne dated plan with furniture and appliance positions.
Finishes and junctionsFloor build-up, skirting profile and dimension changes.
Utilities and wallsRoute photos, a drawing, wall material and reinforcement details.
Delivery and accessDoorway and lift dimensions, building rules and an on-site contact.
Working areaClear assembly space, agreed protection and cleanup.

How to start while renovation is still underway

For custom apartment furniture in Batumi, Georgia, send the plan, room photos and a list of unfinished work. Identify chosen finishes, appliance positions and connections. These details help resolve questions for the builders and establish when the rooms are ready for final measurement.